Project Team
Campus Project Manager: Bill Pace
Demolition Plans Red Chair Architects
Demolition Sabre Demolition
Design: Bullock Smith & Partners
Construction Manager/General Contractor:: Blaine Construction
Project Description
The work at the Stokely/Gibbs site began with the abatement and demolition of Gibbs Hall and Stokely Athletics Center. The cost of this portion of the project is approximately $6,000,000.
A new 335,000 square foot parking garage is being constructed at the site, along with a new student housing facility. The parking garage includes approximately 1,000 spaces within a six-story structure and will serve the housing residents as well as some faculty and staff.
This project also includes substantial re-working of the existing utilities that served Stokely Athletics and Gibbs Hall. The project cost is anticipated to be approximately $32,000,000.
Construction of the new parking garage is slated to be complete August 2016