Project Team

Campus Project Manager: Bill Pace

Demolition Plans Red Chair Architects

Demolition Sabre Demolition

Design: Bullock Smith & Partners

Construction Manager/General Contractor:: Blaine Construction

Project Description

The work at the Stokely/Gibbs site began with the abatement and demolition of Gibbs Hall and Stokely Athletics Center. The cost of this portion of the project is approximately $6,000,000.

A new 335,000 square foot parking garage is being constructed at the site, along with a new student housing facility. The parking garage includes approximately 1,000 spaces within a six-story structure and will serve the housing residents as well as some faculty and staff.

This project also includes substantial re-working of the existing utilities that served Stokely Athletics and Gibbs Hall. The project cost is anticipated to be approximately $32,000,000.

Construction of the new parking garage is slated to be complete August 2016

Project Status: Completed

Square Footage: Approximately 335,000 Square Feet

Start of Construction: August 2014

Completion: Fall 2016

Total Demolition Cost: $6,000,000

Total Garage Cost: $32,000,000